The Road to Progress in Northbrook
All you ever wanted to know about where roadwork is going in Northbrook
The old adage goes something like this "the road to progress is always under construction."
Well here's the progress on some of the roadwork going on in Northbrook:
Techny Road Project
Reconstruction of Techny Road and the installation of new larger storm sewers along this street has begun.
Find out what's happening in Northbrookwith free, real-time updates from Patch.
A conflict junction chamber was installed at the intersection of Techny Road and Butternut Lane.
During construction westbound Techny Road will remain open and traffic will continue to be able to travel north and south on streets intersecting Techny Road with only short duration closures as construction progresses past these streets.
Find out what's happening in Northbrookwith free, real-time updates from Patch.
Techny Road will remain two-way between Second Street and Shermer Road to minimize the impact on Glenbrook North High School and Second Street. Motorists can access the and Northbrook from eastbound Techny Road through June 15th at which time it will be closed for approximately 15 weeks.
Access to Covenant Village from Foxglove Drive will remain open during construction. All other eastbound traffic will be directed to Willow Road as the detour route.
Construction on this phase is expected to continue through 2013.
Annual Asphalt Resurfacing
This year’s program will involve resurfacing and pavement patching (rehabilitation) of approximately four miles of asphalt streets. Specifically, during resurfacing, crews will grind off the road's surface, repair any deficiencies in the road's base and install a new road surface. Defective curbs and gutters will be replaced.
So far, crews have removed curbs on Doriann and Kay Jay drives. Other streets on the program include: Vicki Lane,Ferndale Avenue,Oak Leaf Terrace, Floral Drive,Woodland Drive,Scotch Pine Lane,White Pine Drive, Woodmere Drive, Whisperwoods Court, Acorn Lane, Applewood Lane, Bach Street, Crabtree Lane, Crimson Court, Highland Road, Hunting Lane and Margo Lane.
This effort will continue until Labor Day.